Lefebvre Périchaux Brancion Group - Paris 15

Residentialisation of outdoor spaces

In the 15th arrondissement of Paris, CoBe's landscape designers have requalified the outdoor spaces of the Lefèbvre-Périchaud-Brancion housing complexes.

CoBe - Paris 15 - Lefèbvre Périchaud Brancion group

Objectives of the operation: to rehabilitate as much as possible the existing, to reduce the place of the car, to improve the living environment and the accessibility for all, to create diversified vegetal atmospheres, to use sustainable and quality materials.

CoBe - Poissy écoquartier Rouget-de-Lisle
CoBe - Paris 15 - Lefèbvre Périchaud Brancion group
CoBe - Paris 15 - Lefèbvre Périchaud Brancion group

The project aims to improve a city centre site that has been neglected for many years. We have worked with residents and experts on the issue of transport in order to design a project that integrates the management of flows within the district, while restoring the place of nature.

The original parking area has been transformed into a pedestrian forecourt for a fairground market. Long ashlar steps have been created, linking the forecourt to a large esplanade. Large whistle-stop steps provide access to the future activities and shops on the ground floor for people with reduced mobility.

CoBe - Paris 15 - Lefèbvre Périchaud Brancion group
CoBe - Paris 15 - Lefèbvre Périchaud Brancion group
CoBe - Paris 15 - Lefèbvre Périchaud Brancion group

A garden evoking the presence of the Yerres has been designed below the departmental road. It offers a calm space animated by a few games and a fountain integrated into the steps.

CoBe - Paris 15 - Lefèbvre Périchaud Brancion group
CoBe - Paris 15 - Lefèbvre Périchaud Brancion group
Brancion, CoBe

Reference sheet

Contracting authority

CITALLIOS, City of Epinay-sous-Sénart

CoBe Mission

Complete project management of public spaces and urban coordination.
Urban and landscape monitoring of the implementation
construction and development projects.

Program

Requalification of the outdoor spaces of city center
including on slab

Area

2.5 ha

Cost

7.2 M (overall)
4.5 M€ (Phase 1)

Photos

Patrick H. Müller

Phase 1 delivered in 2020